9706/43/O/N/25 question 1: worked solution (October/November 2025, paper 43)

Show as plain text

Cambridge A2 Level Accounting 9706 · 4.2 Standard costing Worked solution from the Cost and management accounting (A Level) Theory (Paper 4) booklet, Part 2 of 4. Q37 9706/43/O/N/25 original Q1 Structured · 25 marks Worked solution (a) Flex the standards to the actual 10 000 units. Labour hours = 10 000 × 4 = 40 000. Flexible budget for March $ Sales (10 000 × $80) 800 000 Direct materials (10 000 × 3 kilos × $5) (150 000) Direct labour (10 000 × 4 hours × $12) (480 000) [1] Fixed overhead (40 000 hours × $2.50) (100 000) [1] Budgeted profit 70 000 [1] (b)(i) Material price variance = (standard price × actual kilos) − actual cost = ($5 × 31 500) − $149 625 = $7 875 [1] = $7 875 favourable [1] (b)(ii) Material usage variance = (standard kilos for actual output − actual kilos) × standard price = (10 000 × 3 − 31 500) × $5 = $7 500 [1] = $7 500 adverse [1] (b)(iii) Labour rate variance = (standard rate × actual hours) − actual cost = ($12 × 40 500) − $510 300 = $24 300 [1] = $24 300 adverse [1] (b)(iv) Labour efficiency variance = (standard hours for actual output − actual hours) × standard rate = (10 000 × 4 − 40 500) × $12 = $6 000 [1] = $6 000 adverse [1] (c) Write, any two points: Actual production (10 000 units) was greater than budgeted production (8 000 units) , so the fixed overhead was over-absorbed . [1] The variance is the difference between the budgeted fixed overhead and the standard fixed overhead absorbed into production. [1] (Or: it measures how well the fixed capacity was used; a favourable variance shows fixed cost resources were used efficiently.) (d) Selling price variance = $795 000 − (10 000 × $80) = $5 000 adverse (2 marks: figure and direction). Details Favourable $ Adverse $ $ Flexible budget profit 70 000 Selling price variance 5 000 [2] Material price variance 7 875 Material usage variance 7 500 [1] Labour rate variance 24 300 Labour efficiency variance 6 000 [1] Fixed overhead expenditure variance 1 000 Fixed overhead volume variance 20 000 Total variances 27 875 43 800 (15 925) Actual profit 54 075 [1] (e) For continuing , any three: Standard cost is a benchmark to judge actual costs against. [1] Variances are investigated . [1] Corrective action is taken to improve operations. [1] Also accepted (no extra mark): it gives useful information for planning and decisions , for example quoting selling prices. Also accepted (no extra mark): managers become more cost conscious and look for better methods. For stopping , any three: Standards may be artificial if not reviewed and updated regularly. [1] If standards are not realistic , staff are demotivated . [1] It is costly and time consuming to set up standards. [1] Also accepted (no extra mark): managers may be blamed for uncontrollable factors . Decision: advise stopping or continuing, with a supporting comment, for example: continue, because variances show where to take action. [1] KEY IDEA Flex the budget to actual output, calculate each variance, then reconcile flexible budget profit to actual profit. TOTAL 25 marks Official mark scheme VIDEO ▶ Topic lesson A lesson on this topic · by Edex World. Tap the picture to open it on YouTube.