Worked solution from the Cost and management accounting (A Level) Theory (Paper 4) booklet, Part 2 of 4.
Flex the standards to the actual 10 000 units. Labour hours = 10 000 × 4 = 40 000.
| Flexible budget for March | $ |
|---|---|
| Sales (10 000 × $80) | 800 000 |
| Direct materials (10 000 × 3 kilos × $5) | (150 000) |
| Direct labour (10 000 × 4 hours × $12) | (480 000) [1] |
| Fixed overhead (40 000 hours × $2.50) | (100 000) [1] |
| Budgeted profit | 70 000 [1] |
Material price variance = (standard price × actual kilos) − actual cost
= ($5 × 31 500) − $149 625 = $7 875 [1]
= $7 875 favourable [1]
Material usage variance = (standard kilos for actual output − actual kilos) × standard price
= (10 000 × 3 − 31 500) × $5 = $7 500 [1]
= $7 500 adverse [1]
Labour rate variance = (standard rate × actual hours) − actual cost
= ($12 × 40 500) − $510 300 = $24 300 [1]
= $24 300 adverse [1]
Labour efficiency variance = (standard hours for actual output − actual hours) × standard rate
= (10 000 × 4 − 40 500) × $12 = $6 000 [1]
= $6 000 adverse [1]
Write, any two points:
Actual production (10 000 units) was greater than budgeted production (8 000 units), so the fixed overhead was over-absorbed. [1]
The variance is the difference between the budgeted fixed overhead and the standard fixed overhead absorbed into production. [1]
(Or: it measures how well the fixed capacity was used; a favourable variance shows fixed cost resources were used efficiently.)
Selling price variance = $795 000 − (10 000 × $80) = $5 000 adverse (2 marks: figure and direction).
| Details | Favourable $ | Adverse $ | $ |
|---|---|---|---|
| Flexible budget profit | 70 000 | ||
| Selling price variance | 5 000 | [2] | |
| Material price variance | 7 875 | ||
| Material usage variance | 7 500 | [1] | |
| Labour rate variance | 24 300 | ||
| Labour efficiency variance | 6 000 | [1] | |
| Fixed overhead expenditure variance | 1 000 | ||
| Fixed overhead volume variance | 20 000 | ||
| Total variances | 27 875 | 43 800 | (15 925) |
| Actual profit | 54 075 [1] |
For continuing, any three:
Standard cost is a benchmark to judge actual costs against. [1]
Variances are investigated. [1]
Corrective action is taken to improve operations. [1]
Also accepted (no extra mark): it gives useful information for planning and decisions, for example quoting selling prices.
Also accepted (no extra mark): managers become more cost conscious and look for better methods.
For stopping, any three:
Standards may be artificial if not reviewed and updated regularly. [1]
If standards are not realistic, staff are demotivated. [1]
It is costly and time consuming to set up standards. [1]
Also accepted (no extra mark): managers may be blamed for uncontrollable factors.
Decision: advise stopping or continuing, with a supporting comment, for example: continue, because variances show where to take action. [1]