Cambridge A2 Level Accounting 9706 · 4.2 Standard costing

Q37 · 9706/43/O/N/25 Q1

Worked solution from the Cost and management accounting (A Level) Theory (Paper 4) booklet, Part 2 of 4.

Q379706/43/O/N/25original Q1Structured · 25 marks
Question 1 from 9706/43/O/N/25

Worked solution

(a)

Flex the standards to the actual 10 000 units. Labour hours = 10 000 × 4 = 40 000.

Flexible budget for March$
Sales (10 000 × $80)800 000
Direct materials (10 000 × 3 kilos × $5)(150 000)
Direct labour (10 000 × 4 hours × $12)(480 000) [1]
Fixed overhead (40 000 hours × $2.50)(100 000) [1]
Budgeted profit70 000 [1]

(b)(i)

Material price variance = (standard price × actual kilos) − actual cost

= ($5 × 31 500) − $149 625 = $7 875 [1]

= $7 875 favourable [1]

(b)(ii)

Material usage variance = (standard kilos for actual output − actual kilos) × standard price

= (10 000 × 3 − 31 500) × $5 = $7 500 [1]

= $7 500 adverse [1]

(b)(iii)

Labour rate variance = (standard rate × actual hours) − actual cost

= ($12 × 40 500) − $510 300 = $24 300 [1]

= $24 300 adverse [1]

(b)(iv)

Labour efficiency variance = (standard hours for actual output − actual hours) × standard rate

= (10 000 × 4 − 40 500) × $12 = $6 000 [1]

= $6 000 adverse [1]

(c)

Write, any two points:

Actual production (10 000 units) was greater than budgeted production (8 000 units), so the fixed overhead was over-absorbed. [1]

The variance is the difference between the budgeted fixed overhead and the standard fixed overhead absorbed into production. [1]

(Or: it measures how well the fixed capacity was used; a favourable variance shows fixed cost resources were used efficiently.)

(d)

Selling price variance = $795 000 − (10 000 × $80) = $5 000 adverse (2 marks: figure and direction).

DetailsFavourable $Adverse $$
Flexible budget profit70 000
Selling price variance5 000[2]
Material price variance7 875
Material usage variance7 500[1]
Labour rate variance24 300
Labour efficiency variance6 000[1]
Fixed overhead expenditure variance1 000
Fixed overhead volume variance20 000
Total variances27 87543 800(15 925)
Actual profit54 075 [1]

(e)

For continuing, any three:

Standard cost is a benchmark to judge actual costs against. [1]

Variances are investigated. [1]

Corrective action is taken to improve operations. [1]

Also accepted (no extra mark): it gives useful information for planning and decisions, for example quoting selling prices.

Also accepted (no extra mark): managers become more cost conscious and look for better methods.

For stopping, any three:

Standards may be artificial if not reviewed and updated regularly. [1]

If standards are not realistic, staff are demotivated. [1]

It is costly and time consuming to set up standards. [1]

Also accepted (no extra mark): managers may be blamed for uncontrollable factors.

Decision: advise stopping or continuing, with a supporting comment, for example: continue, because variances show where to take action. [1]

KEY IDEAFlex the budget to actual output, calculate each variance, then reconcile flexible budget profit to actual profit.
TOTAL 25 marks

Official mark scheme

Mark scheme for 9706/43/O/N/25 question 1