9706/43/O/N/23 question 1: worked solution (October/November 2023, paper 43)
Show as plain textHide plain text
Cambridge A2 Level Accounting 9706 · 4.2 Standard costing Worked solution from the Cost and management accounting (A Level) Theory (Paper 4) booklet, Part 2 of 4. Q30 9706/43/O/N/23 original Q1 Structured · 25 marks Worked solution (a) The flexible budget changes the fixed budget to the actual activity of 2 180 units. Each fixed-budget figure is divided by 2 000 units and multiplied by 2 180 units. Details $ Sales revenue ($184 000 ÷ 2 000 × 2 180) 200 560 Direct materials ($84 000 ÷ 2 000 × 2 180) 91 560 Direct labour ($60 000 ÷ 2 000 × 2 180) 65 400 [1] Fixed overhead ($18 000 ÷ 2 000 × 2 180) 19 620 [1] Total cost 176 580 Budgeted profit 23 980 [1] Budgeted profit = $200 560 − $176 580 = $23 980. (b)(i) Sales price variance = (actual units × budgeted price) − actual revenue Budgeted price = $184 000 ÷ 2 000 = $92 = (2 180 × $92) − $196 200 = $200 560 − $196 200 = $4 360 [1] The actual revenue is less than expected, so it is adverse . [1] (b)(ii) Sales volume variance = (actual units − budgeted units) × budgeted profit per unit Budgeted profit per unit = $22 000 ÷ 2 000 = $11 = (2 180 − 2 000) × $11 = $1 980 [1] More units were sold than budgeted, so it is favourable . [1] (b)(iii) Fixed overhead expenditure variance = actual fixed overhead − budgeted fixed overhead = $18 400 − $18 000 = $400 [1] Actual overhead is higher than budgeted, so it is adverse . [1] (b)(iv) Fixed overhead volume variance = absorbed (flexible budget) fixed overhead − budgeted fixed overhead = $19 620 (own figure from (a)) − $18 000 = $1 620 [1] More was absorbed than budgeted, so it is favourable . [1] (c) Start with the flexible budgeted profit and add or subtract each variance (adverse in brackets, favourable added) to reach the actual profit. Details $ Flexible budgeted profit 23 980 [1] Sales price variance (4 360) A [1] Direct materials variance ($113 796 − $91 560) (22 236) A [1] Direct labour variance ($65 400 − $55 590) 9 810 F [2] Fixed overhead expenditure (400) A Fixed overhead volume 1 620 F [1] Actual profit 8 414 [1] Check: 23 980 − 4 360 − 22 236 + 9 810 − 400 + 1 620 = 8 414. (d) Advise means: give the calculations and the points for each supplier, then a decision with a comment. Calculations: Material cost per unit: supplier A = 2.8 kilos × $13.75 = $38.50; supplier B = 2.5 kilos × $15.40 = $38.50. The unit cost is the same for both. [1] The $38.50 is lower than both the budgeted cost of $42 ($84 000 ÷ 2 000) and the actual cost of $52.20 ($113 796 ÷ 2 180). [1] Comments: Supplier B's materials are of better quality than A's. [1] This is because there is less wastage . [1] Poor quality material from A may reduce the efficiency of workers and the quality of the final product. [1] Supplier B may bring extra costs such as import duty, freight and insurance. [1] Decision: choose supplier B , because the unit cost is the same as A's but the quality is better with less wastage. [1] Other valid points are also accepted, for example the unit price of A is lower, or delivery from B takes longer for an urgent order. KEY IDEA A flexible budget restates the fixed budget at actual output so that variances explain the move from budgeted profit to actual profit. TOTAL 25 marks Official mark scheme VIDEO ▶ Whole paper Video solution of the whole paper · by IGCSE / AS LEVEL / A LEVEL MATHS AND ACCOUNTS. Tap the picture to open it on YouTube.