9706/42/F/M/24 question 2: worked solution (February/March 2024, paper 42)

Show as plain text

Cambridge A2 Level Accounting 9706 · 4.2 Standard costing Worked solution from the Cost and management accounting (A Level) Theory (Paper 4) booklet, Part 2 of 4. Q31 9706/42/F/M/24 original Q2 Structured · 25 marks Worked solution (a) The fixed budget is for 8 000 units. The flexible budget is for the actual 7 000 units. Fixed overheads are absorbed at $2.50 per labour hour (4 hours per unit). Workings: W1 Direct labour: 8 000 × 4 = 32 000 hours × $6 = $192 000; 7 000 × 4 = 28 000 hours × $6 = $168 000. Details Fixed budget $ Flexible budget $ Sales revenue 544 000 476 000 [1] Direct material (96 000) (84 000) [1] Direct labour W1 (192 000) (168 000) [1] Fixed overheads (80 000) (70 000) [1] Profit 176 000 154 000 [1] Fixed overheads: 32 000 × $2.50 = $80 000 and 28 000 × $2.50 = $70 000. (b)(i) Direct material price variance = actual kilos × (standard price − actual price) Actual kilos = 7 000 × 3.1 = 21 700; actual price = $82 460 ÷ 21 700 = $3.80 = 21 700 × ($4 − $3.80) = $4 340 [1] The actual price is lower, so it is favourable . [1] (b)(ii) Direct material usage variance = standard price × (standard kilos for actual output − actual kilos) Standard kilos = 7 000 × 3 = 21 000 = $4 × (21 700 − 21 000) = $2 800 [1] More material was used than standard, so it is adverse . [1] (b)(iii) Direct labour rate variance = actual hours × (standard rate − actual rate) Actual hours = $182 700 ÷ $5.80 = 31 500 = 31 500 × ($6 − $5.80) = $6 300 [1] The actual rate is lower, so it is favourable . [1] (b)(iv) Direct labour efficiency variance = standard rate × (standard hours for actual output − actual hours) Standard hours = 7 000 × 4 = 28 000 = $6 × (28 000 − 31 500) = $21 000 [1] More hours were used than standard, so it is adverse . [1] (c) Explain means: give the point, then why. The volume variance splits into a capacity variance and an efficiency variance. The fixed overhead volume variance was adverse because actual production was less than budgeted production . [1] The fixed overhead capacity variance was adverse [1] because actual hours worked were less than the hours in the fixed budget : 31 500 hours is less than 32 000 hours. [1] The fixed overhead efficiency variance was adverse [1] because actual hours worked were greater than the hours in the flexible budget : 31 500 hours is more than 28 000 hours. [1] (d) Advise means: give the points for and against, then a decision with a comment. For (any three): A trade receivables and trade payables budget predicts cash inflows and cash outflows . [1] It makes it possible to prepare a cash budget . [1] It helps in producing the master budget and budgeted statement of financial position . [1] Against (any three): The company may make all its sales and purchases on a cash basis . [1] It is more time consuming and raises administrative costs. [1] The budget will not make receivables pay or stop irrecoverable debts. [1] Decision: write yes or no and support it, for example: yes, start the budgets, because cash is often more important than profit and the budgets let the company plan its cash. [1] KEY IDEA Variances compare actual results with the flexible budget, and the fixed overhead volume variance splits into capacity and efficiency. TOTAL 25 marks Official mark scheme VIDEO ▶ Whole paper Video solution of the whole paper · by IGCSE / AS LEVEL / A LEVEL MATHS AND ACCOUNTS. Tap the picture to open it on YouTube.