9706/12/F/M/23 question 24: worked solution (February/March 2023, paper 12)

Show as plain text

Cambridge AS Level Accounting 9706 · 2.2 Traditional costing methods Worked solution from the Cost and management accounting (AS Level) MCQ booklet. Q212 9706/12/F/M/23 original Q24 Multiple choice Worked solution The question asks for the actual profit on the job. Estimated labour hours = $200 ÷ $20 = 10 hours Actual hours = 10 × 125% = 12.5 hours Actual labour = 12.5 × $20 = $250 Actual overheads = 12.5 × $10 = $125 Actual cost = $680 + $250 + $125 = $1 055 Actual profit = $1 260 − $1 055 = $205 So the answer is A . B , C and D do not change both labour and overheads for the extra hours. KEY IDEA Extra labour hours raise both labour cost and overheads absorbed per labour hour. ANSWER A VIDEO ▶ Starts at Q24 (36:16) Starts at Q24 (36:16) · by Study with Prashna. Tap the picture to open it on YouTube.