Worked solution from the Cost and management accounting (AS Level) MCQ booklet.
The question asks for the actual profit on the job.
Estimated labour hours = $200 ÷ $20 = 10 hours
Actual hours = 10 × 125% = 12.5 hours
Actual labour = 12.5 × $20 = $250
Actual overheads = 12.5 × $10 = $125
Actual cost = $680 + $250 + $125 = $1 055
Actual profit = $1 260 − $1 055 = $205
So the answer is A.
B, C and D do not change both labour and overheads for the extra hours.