Cambridge AS Level Accounting 9706 · 2.2 Traditional costing methods

Q212 · 9706/12/F/M/23 Q24

Worked solution from the Cost and management accounting (AS Level) MCQ booklet.

Q2129706/12/F/M/23original Q24Multiple choice
Question 24 from 9706/12/F/M/23

Worked solution

The question asks for the actual profit on the job.

Estimated labour hours = $200 ÷ $20 = 10 hours

Actual hours = 10 × 125% = 12.5 hours

Actual labour = 12.5 × $20 = $250

Actual overheads = 12.5 × $10 = $125

Actual cost = $680 + $250 + $125 = $1 055

Actual profit = $1 260 − $1 055 = $205

So the answer is A.

B, C and D do not change both labour and overheads for the extra hours.

KEY IDEAExtra labour hours raise both labour cost and overheads absorbed per labour hour.
ANSWER A
VIDEO
▶ Starts at Q24 (36:16)

Starts at Q24 (36:16) · by Study with Prashna. Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.