9609/31/O/N/23 question 3: worked solution (October/November 2023, paper 31)

Show as plain text

Cambridge A2 Level Business 9609 · 9.3 Operations strategy Worked solution from the Operations management Theory (Paper 3) booklet, Part 3 of 3. Q39 9609/31/O/N/23 original Q3 Structured · 16 marks Worked solution (a) The minimum project duration is the length of the critical path (the longest route through the network): A → C → E → F → G. 4 + 5 + 1 + 2 + 1 = 13 weeks [1] (b) Total float = latest finish time (LFT) − duration − earliest start time (EST). Activity D can start only when A is finished, so its EST is 4 weeks. F and G take 3 weeks, so the event at the end of D must be done by week 13 − 3 = 10 (LFT). Total float = LFT − duration − EST [1] = 10 − 1 − 4 [1] = 5 weeks [1] (c) Start with knowledge : critical path analysis (CPA) uses a network diagram to find the critical path and the minimum project time (13 weeks here). Floats show which activities can be delayed without delaying the whole project. CPA helps planning, shows start times and lets managers monitor progress and take corrective action if a delay is found. Application: CP's objective is to minimise interruption to production so that retailers have a continuous supply. The new line for external-use paint is being installed, and the contractor produced the CPA. The contract was agreed on the basis that Table 1.1 and Fig. 1.1 are accurate and reliable. Analysis: CPA gives timings to every activity, so CP can plan and monitor the installation and make sure it does not over-run. CP can see how long production will be stopped and build up inventory before work starts, so sales go on as normal and there are no unmet orders or lost sales and profit. CP can watch the critical activities, such as E (delivery of components), and act if a delay is threatened, so the project finishes on time and production is interrupted as little as possible. Against: the contractor won the work on the lowest price and produced the CPA itself, so it may have used optimistic timings to get the contract. A late project would mean delays and disappointed customers. A CPA is only as good as its data and the skills of the person who made it, and it does not ensure good management. Evaluation: CPA helps but cannot ensure that interruption is minimised. It depends on how accurate the data is. The contract says the CPA must be accurate and reliable, so it is more likely to be right because the contractor will want to avoid penalty fees. But CP is experienced in making paint, not in installing production lines, so it may not know whether the CPA is accurate. Other factors matter too, such as staff training, which the CPA does not cover. Conclusion: CPA is very useful for planning the installation of the external-paint line, but CP should not rely on it alone. It should check progress against the plan before and after work starts, so that supply to retailers is continuous. This earns the top level for knowledge: developed knowledge of CPA and its benefits and limitations. [2] It earns the top level for application: developed application to CP (continuous supply to retailers, the contractor's CPA, the contract). [2] It earns the top level for analysis: developed analysis with two or more links in the chain (timings → monitoring → no over-run → continuous supply) and a two-sided view. [2] It reaches the top level for evaluation: a developed judgement in the business context that balances the arguments (contract terms and accuracy against CP's lack of experience and the limits of CPA). [6] KEY IDEA CPA shows the minimum project time and which activities can slip, but it is only as good as its data, so it helps rather than ensures continuous production. TOTAL 16 marks Official mark scheme VIDEO ▶ Whole paper Video solution of the whole paper · by EconoBuz by Osama Musani. Tap the picture to open it on YouTube.