9609/32/O/N/23 question 3: worked solution (October/November 2023, paper 32)

Show as plain text

Cambridge A2 Level Business 9609 · 9.3 Operations strategy Worked solution from the Operations management Theory (Paper 3) booklet, Part 3 of 3. Q40 9609/32/O/N/23 original Q3 Structured · 16 marks Worked solution (a) Capacity utilisation = output ÷ maximum capacity × 100 = 120 000 ÷ 160 000 × 100 = 75% [1] (b) Inventory turnover = cost of sales ÷ average inventory, and cost of sales = revenue − gross profit. Cost of sales = $1.2m − $0.8m = $0.4m [1] Inventory turnover = 0.4 ÷ 0.13 [1] = 3.08 times (about 3 times) [1] (c) Knowledge: lean production means reducing all forms of waste. Its techniques include just in time (JIT) , total quality management (TQM), quality circles, cell production and kaizen (continuous improvement). It may need investment, for example in ERP or flexible machines. CQ's objectives are to reach full capacity within eight months while reducing the workforce, to cut defective output by 50% and to raise inventory turnover to five times a year. Application: CQ has only just taken over an unprofitable factory. Inventory turnover is 3.08, so inventory is held for about 119 days (the target is 5 times). 5% of output is defective, which is 6 000 units in six months. Unions have agreed to lean production if there is training. Supply chain failures caused the high inventory. Analysis: lean production reduces waste, so CQ becomes more efficient, unit costs fall and CQ becomes more competitive. TQM and quality circles give workers responsibility for quality. This may raise motivation, cut defects and improve quality and productivity. JIT aims at zero inventory, so inventory turnover rises and holding costs fall. Better supplier relationships could remove the supply chain failures that caused the high inventory. Lean production uses less of everything, so output can be kept up with fewer workers, which lowers unit costs. Training adds cost, but it may raise motivation and productivity. Against: JIT may leave CQ without materials and lose sales. Bamboo comes from the US, so long lead times make JIT hard. Evaluation: lean production will help with all three objectives, but it may not be enough on its own. The result depends on supplier reliability, because bamboo is shipped from the US. It depends on whether CQ can forecast demand, because JIT risks lost customers if demand is underestimated. It depends on the cost of training and investment given CQ's high gearing, and on whether workers, new to the bamboo shoes after the takeover, accept new methods. Other approaches such as investment in capital equipment, or more marketing to raise sales and inventory turnover, may also be needed. Conclusion: lean production is likely to be necessary but not sufficient. It should be combined with reliable suppliers and investment if the objectives are to be met within eight months. This earns the top level for knowledge: developed knowledge of lean production and of the effect on the objectives. [2] It earns the top level for application: developed application to CQ twice or more (inventory turnover, 5% defects, the takeover, the unions). [2] It earns the top level for analysis: developed analysis with two or more links in the chain. [2] It reaches the top level for evaluation: a developed judgement in context, balancing the arguments and saying what the outcome depends on. [6] KEY IDEA Lean production cuts waste, defects and inventory, but CQ's objectives also depend on suppliers, demand forecasts, cost and other investment. TOTAL 16 marks Official mark scheme VIDEO ▶ Whole paper Video solution of the whole paper · by Cambridge Online Tutor for O Level & A level. Tap the picture to open it on YouTube.