9706/22/O/N/23 question 4: worked solution (October/November 2023, paper 22)
Show as plain textHide plain text
Cambridge AS Level Accounting 9706 · 2.2 Traditional costing methods Worked solution from the Cost and management accounting (AS Level) Theory (Paper 2) booklet, Part 2 of 2. Q33 9706/22/O/N/23 original Q4 Structured · 30 marks Worked solution (a) Apportion each overhead on a fair basis: indirect wages by number of indirect employees (20 in total, so $420 000 ÷ 20 = $21 000 each); factory rent and rates by floor space (12 000 m², so $30 000 ÷ 12 000 = $2.50 a m²); machine overheads by machine hours (34 300 + 25 700 = 60 000 hours, as the question says). Then share the Stores total over the departments that use it, by number of orders (2 100 + 1 600 + 500 = 4 200), and the Maintenance total over the production departments by call outs (210 + 40 = 250). Details Total $ Machining $ Assembly $ Stores $ Maintenance $ Indirect wages 420 000 84 000 252 000 42 000 42 000 [1] Factory rent and rates 30 000 10 000 14 000 4 500 1 500 [1] Machine overheads 22 000 12 577 9 423 – – [1] Total overheads 472 000 106 577 275 423 46 500 43 500 Apportion Stores – 23 250 17 714 (46 500) 5 536 [1] Subtotal 472 000 129 827 293 137 – 49 036 Apportion Maintenance – 41 190 7 846 – (49 036) [1] Total overhead costs 472 000 171 017 300 983 – – [1] The two service departments are cleared to nil, so the whole $472 000 now sits in the two production departments (own figures count if the Stores share is worked from your own totals). (b) Overhead absorption rate = total overheads of the department ÷ budgeted activity (the hours that best match how the work is done). Machining is machine based, so use machine hours : $171 017 ÷ 34 300 hours = $4.99 per machine hour (rate, and machine hours as the basis) [2] Assembly is labour based, so use direct labour hours : $300 983 ÷ 77 700 hours = $3.87 per direct labour hour (rate, and labour hours as the basis) [2] (c) Overhead absorbed = actual hours × absorption rate. Compare it with the actual overheads. Details Machining $ Assembly $ Actual overheads 226 952 267 465 Absorbed: 44 120 × $4.99 220 159 Absorbed: 72 580 × $3.87 280 885 Machining: $226 952 − $220 159 = $6 793 under-absorbed (too little overhead was charged to the work) [2] Assembly: $280 885 − $267 465 = $13 420 over-absorbed (too much overhead was charged to the work) [2] (d) For the special order, change each cost as the question says. Assembly labour is paid at the usual $12 plus 25% overtime premium = $15 an hour. Details Working $ Direct materials $45.60 × 1.3 59.28 [1] Direct labour: Machining 30 min × 1.5 = 45 min; 0.75 h × $10 7.50 [1] Direct labour: Assembly 105 + 15 = 120 min; 2 h × $15 30.00 [1] Total direct cost of one bicycle 96.78 [1] (e) Total cost = direct cost + overheads absorbed. A 30% gross profit margin means profit is 30% of the selling price, so profit = total cost × 30/70. Details Working $ Direct cost $96.78 × 120 11 613.60 [1] Machining overheads $4.99 × 20 min (1/3 h) × 120 199.60 [1] Assembly overheads $3.87 × 120 min (2 h) × 120 928.80 [1] Total cost 12 742.00 Gross profit $12 742.00 × 30/70 5 460.86 [1] Quoted selling price 18 202.86 [1] Working per bicycle (unit basis) is also accepted: $96.78 + $1.66 + $7.74 = $106.18 a unit, × 120 = $12 741.60, which gives a price of about $18 202. (f) Give points for and against, then your decision. Write any six comments in all. Reasons to accept The new customer may become a major customer over time. [1] The terms offered will still produce a profit for the business. [1] Reasons to reject Two months' credit may make the business's cash flow difficulties worse . [1] Existing customers may try to negotiate better credit terms too. [1] Andreas cannot be sure the regular orders will continue . [1] The 10% discount means the work will not give the 30% gross profit margin he wants. [1] Advice: Andreas should reject the terms (cash flow is already hard to manage and the margin falls below 30%), supported by the comments above. [1] Another valid decision with valid comments (for example, accept only after checking the customer's creditworthiness) also earns the advice mark. KEY IDEA Share service-department overheads fairly, absorb them using hours that match the work, and price an order from its total cost with the profit margin worked on the selling price. TOTAL 30 marks Official mark scheme VIDEO ▶ Starts at Q4 (1:37:49) Starts at Q4 (1:37:49) · by Sir Waleed Khanzada. Tap the picture to open it on YouTube.