9706/12/M/J/21 question 23: worked solution (May/June 2021, paper 12)
Show as plain textHide plain text
Cambridge AS Level Accounting 9706 · 2.2 Traditional costing methods Worked solution from the Cost and management accounting (AS Level) MCQ booklet. Q138 9706/12/M/J/21 original Q23 Multiple choice Worked solution The question asks by how much overheads were over- or under-absorbed on machine hours. Overhead absorption rate (OAR) = budgeted overheads ÷ budgeted activity (hours or units). OAR = $900 000 ÷ 6 000 = $150 per machine hour . Absorbed = 6 200 × $150 = $930 000 . Actual overheads = $960 000. $960 000 − $930 000 = $30 000 under-absorbed . So the answer is B . A has the right amount but the wrong direction. C and D use the wrong amount ($60 000, the difference between actual and budgeted overheads). KEY IDEA Under-absorbed = overheads incurred − overheads absorbed, when incurred is larger. ANSWER B VIDEO ▶ Starts at Q23 (38:03) Starts at Q23 (38:03) · by Study with Prashna. Tap the picture to open it on YouTube.