The question asks by how much overheads were over- or under-absorbed on machine hours.

Overhead absorption rate (OAR) = budgeted overheads ÷ budgeted activity (hours or units).

OAR = $900 000 ÷ 6 000 = $150 per machine hour.

Absorbed = 6 200 × $150 = $930 000.

Actual overheads = $960 000.

$960 000 − $930 000 = $30 000 under-absorbed.

So the answer is B.

A has the right amount but the wrong direction. C and D use the wrong amount ($60 000, the difference between actual and budgeted overheads).

KEY IDEAUnder-absorbed = overheads incurred − overheads absorbed, when incurred is larger.
ANSWER B
VIDEO
▶ Starts at Q23 (38:03)

Starts at Q23 (38:03) · by Study with Prashna. Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.