Cambridge A2 Level Business 9609 · 9.3 Operations strategy

Q24 · 9609/31/M/J/21 Q4

Worked solution from the Operations management Theory (Paper 3) booklet, Part 3 of 3.

Q249609/31/M/J/21original Q4Structured · 20 marks
Question 4 from 9609/31/M/J/21

Worked solution

(a)(i)

EST of an activity = EST of the activity before it + that activity's duration. Activity F follows E, and E follows A. [1]

EST of F = 18 + 3 = 21 days [1]

(a)(ii)

Total float is the longest time an activity can be delayed without delaying the whole project. Formula: total float = LFT − duration − EST [1]

Activity D: = 21 − 2 − 0 [1]

= 19 days [1]

(a)(iii)

Free float is the longest time an activity can be delayed without delaying the next activity. Formula: free float = EST of next activity − duration − EST [1]

Activity C: = 18 − 6 − 0 [1]

= 12 days [1]

(b)

Knowledge: critical path analysis (CPA), also called network analysis, is part of project management. It lists all the tasks in a project, puts them in order and finds the critical path. This helps resources to be used efficiently.

Application: Appendix 1 shows a minimum time of 28 days, and the critical path is A, E, F, H. Peter wants the machines installed within one month, so CPA shows the deadline can be met. The non-critical activities B, C, D and G have float, so managers can concentrate on the critical ones. PGC's marketing plan starts one week after installation, so key dates matter.

Analysis 1: CPA gives the project length so key dates can be set and activities planned. It shows start times, so the right resources (for example the installers) are ready at the right time.

Analysis 2: it gives latest finish times, so progress can be checked and action taken if an activity falls behind. Knowing the float tells managers what a delay would cost, so they can move resources and keep the new roasters ready on time and protect current production. This lets PGC use the extra capacity to expand, for example into cafés.

Analysis 3: CPA could set targets that are too tight. Workers who rush to meet them may make mistakes in the installation.

Evaluation: CPA is only as good as its data. The production manager is young and newly qualified, so is she the best person to prepare it? Durations are hard to estimate, and the contractor may need to give input. The cost of CPA is small compared with the cost of the project. But for a small, simple project with only eight activities, it may not be worth much.

Judgement: CPA played a useful part, because it shows the 28 days fit inside Peter's deadline and which activities must not be late. However, its value depends on how accurate the durations are, and the project is simple enough that careful management would also have worked.

This earns the top level for knowledge: it gives CPA, the critical path and what it does. [2]

This earns the top level for application: it applies two or more points to the case (28 days against Peter's one-month deadline, critical path AEFH, non-critical activities, the new production manager). [2]

This earns the top level for analysis: good use of theory and reasoned argument, each point followed through from cause to effect to consequence for the business. [4]

This earns the top level for evaluation: good judgement with a well supported conclusion (depends on the data and who prepared it, and on whether CPA is worth it for a small project). [4]

KEY IDEACritical path analysis shows the shortest project time and which tasks cannot be late, but it is only as good as its data.
TOTAL 20 marks

Official mark scheme

Mark scheme for 9609/31/M/J/21 question 4