Worked solution from the Cost and management accounting (AS Level) MCQ booklet.
The question asks for the cost of the batch of padded chairs.
Basic cost = 1 000 chairs × $70 = $70 000
Extra materials = $6 000
Extra labour = 500 hours × $15 = $7 500
Extra overheads = $2 000
Cost of the batch = $70 000 + $6 000 + $7 500 + $2 000 = $85 500
So the answer is D.
A ($13 500) counts only the extra materials and labour, and B ($15 500) counts only the extra costs. C ($83 500) leaves out the extra overheads.