Worked solution from the Cost and management accounting (A Level) Theory (Paper 4) booklet, Part 1 of 4.
Write: activity based costing uses cost drivers [1]
which are based on activities [1]
that cause overheads to be incurred, so overheads are grouped in cost pools and charged to products by their use of each activity. [1]
Overhead absorption rate = total budgeted overheads ÷ total direct labour hours
Hours = (5 000 × 4) + (8 000 × 1.5) = 20 000 + 12 000 = 32 000
= $216 000 ÷ 32 000 = $6.75 per direct labour hour [1]
Direct labour: M1 = 5 000 × 4 × $15 = $300 000; V1 = 8 000 × 1.5 × $15 = $180 000. Direct materials: M1 = 5 000 × $35 = $175 000; V1 = 8 000 × $26 = $208 000. Fixed overhead (W1): M1 = 5 000 × 4 × $6.75 = $135 000; V1 = 8 000 × 1.5 × $6.75 = $81 000. Selling price = total cost + 50% mark-up.
| Details | M1 $ | V1 $ |
|---|---|---|
| Sales revenue (total cost × 150%) | 915 000 | 703 500 [1] |
| Direct materials | 175 000 | 208 000 [1] |
| Direct labour | 300 000 | 180 000 [1] |
| Fixed overhead (W1) | 135 000 | 81 000 [2] |
| Total cost | 610 000 | 469 000 [1] |
| Profit | 305 000 | 234 500 [1] |
W1 Overheads shared by each cost driver:
| Cost pool | M1 $ | V1 $ |
|---|---|---|
| Handling purchases ($43 200 × 20/45; × 25/45) | 19 200 | 24 000 [1] |
| Inspecting and testing ($28 800 × 20/50; × 30/50) | 11 520 | 17 280 [1] |
| Supervising (direct labour hours: $96 000 × 20 000/32 000; × 12 000/32 000) | 60 000 | 36 000 [1] |
| Setting up machines ($48 000 × 12/30; × 18/30) | 19 200 | 28 800 [1] |
| Total | 109 920 | 106 080 |
Statement of profit or loss using ABC
| Details | M1 $ | V1 $ |
|---|---|---|
| Sales revenue (total cost × 150%) | 877 380 | 741 120 [1] |
| Direct materials | 175 000 | 208 000 |
| Direct labour | 300 000 | 180 000 |
| Fixed overhead (W1) | 109 920 | 106 080 |
| Total cost | 584 920 | 494 080 [1] |
| Profit | 292 460 | 247 040 [1] |
Calculations: selling price per unit.
Single absorption rate: M1 = $915 000 ÷ 5 000 = $183 [1]
V1 = $703 500 ÷ 8 000 = $87.94 [1]
ABC: M1 = $877 380 ÷ 5 000 = $175.48 [1]
V1 = $741 120 ÷ 8 000 = $92.64 [1]
Comments: with the single rate M1 is overpriced and V1 is underpriced (under ABC M1's price falls and V1's price rises). [1]
Overpricing makes M1 less competitive; underpricing V1 loses revenue and profit. [1]
Decision: adopt ABC for setting selling prices, because with a single rate M1 is overpriced and V1 is underpriced; but the cost and benefit of running the ABC system must be evaluated. [1]
(Other valid responses are accepted.)