Worked solution from the Cost and management accounting (AS Level) MCQ booklet.
The question asks what type of cost it is when one supervisor is needed up to 5 000 units and two supervisors beyond that.
The cost is fixed within a range of output, then jumps to a higher fixed amount. This is a stepped cost.
So the answer is C.
A is wrong because the cost changes at 5 000 units. B is wrong because there is no part that varies with each unit. D is wrong because the cost does not move with each extra unit.
▶ Starts at Q21 (39:21)
Starts at Q21 (39:21) · by Study with Prashna. Tap the picture to open it on YouTube.
Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.