Worked solution from the Cost and management accounting (AS Level) MCQ booklet.
The question asks for the job cost before profit: materials + labour + overheads absorbed.
Overhead absorption rate = budgeted overheads ÷ budgeted direct labour hours = $20 000 ÷ 2 000 = $10 per hour
Direct materials = $45
Direct labour = 6 hours × $20 = $120
Overheads = 6 hours × $10 = $60
Cost of job = $45 + $120 + $60 = $225
So the answer is D.
A ($105) adds only the materials and the overheads and leaves out labour. B ($165) leaves out the overheads. C ($180) leaves out the materials. D is the full cost.