Worked solution from the Operations management Theory (Paper 3) booklet, Part 3 of 3.
Node 5 is the end of Activity G. Work forwards for the earliest start time (EST) and backwards for the latest finish time (LFT).
EST = 5 (Activity A) + 24 (Activity G) = 29 [1]
LFT = 43 − 10 (Activity H) = 33 [1]
Read the finish node of the network diagram: the minimum project duration is 43 days [1]
The critical path is the route with no float: A, C, D, F, K [1]
Total float = LFT of J − duration of J − EST of J
= 43 − 30 − 5 [1]
= 8 days [1]
If you use your own answer to (a)(ii) as the LFT, follow the same method with that figure.
Evaluate means: give the uses and limits of critical path analysis (CPA) for UBH, then judge how useful it is.
Knowledge: CPA (network analysis) is part of project management. It lists every task, puts the tasks in the correct order and shows the critical path. It plans when resources are needed, sets targets, forces managers to plan carefully and shows which activities need most attention. Its limits: it needs other techniques to manage resources, the plan is only as good as the management behind it, and for a new project durations involve guesswork.
Application: Table 2 lists the activities for Beehive 811. Fixtures and fittings can be ordered to arrive just in time for installation, for example office equipment (Activity E) can wait 15 days because it has total and free float of 15 days. Activities G and H (recruitment and training) have 4 days of total float. The delay in the delivery of office equipment can be checked against the 43-day minimum time. This is UBH's 11th beehive, so it has experience of managing projects.
Analysis: planning when resources are needed means they are used well, which saves time and money and raises profit. Ordering fixtures just in time delays cash outflows.
Clear targets may motivate staff, making it more likely that the beehive opens on time. UBH can tell customers the opening date, so they are not dissatisfied, revenue rises and capacity utilisation is higher at opening.
If the project falls behind, managers may move resources from non-critical activities to critical ones. This could stop prospective customers going to other co-working spaces and so prevent a loss of income.
Evaluation: the network is fairly simple and more detail is needed. CPA does not guarantee that the project finishes on time, and outside events UBH cannot control can disrupt the opening. UBH has experience of planning building work, so its estimates should be fairly accurate.
UBH controls only some activities (G and H), while others such as building work (D) may be done by subcontractors. It may not be possible to move resources, for example labour cannot be moved from recruitment (G) to building work (D). If management is poor, even a good CPA will not ensure success.
Overall CPA is very useful for planning and for spotting float and critical activities, but its value depends on good management and on accurate times.
This earns the top level for knowledge: two relevant points about CPA, its benefits and its limits. [2]
It earns the top level for application: it uses two points from the case, the float figures in Table 2 and the delayed delivery. [2]
It reaches the top level for analysis: good reasoned argument on how CPA saves time and money, keeps customers informed and allows resources to be moved. [4]
It reaches the top level for evaluation: a supported judgement on usefulness, with what it depends on. [4]