Worked solution from the Cost and management accounting (AS Level) MCQ booklet.
The question asks for the price quoted for the job.
Materials = $10 000.
Design labour = 10 × $125 = $1 250. Assistant labour = 100 × $70 = $7 000.
Overheads are absorbed per labour hour: total hours = 10 + 100 = 110, so 110 × $50 = $5 500.
Total cost = $10 000 + $1 250 + $7 000 + $5 500 = $23 750.
Mark-up 20% = $23 750 × 0.20 = $4 750.
Price = $23 750 + $4 750 = $28 500.
So the answer is D.
B is the cost without the mark-up. A and C do not come from the working.