Cambridge AS Level Accounting 9706 · 2.2 Traditional costing methods

Q39 · 9706/21/O/N/24 Q4

Worked solution from the Cost and management accounting (AS Level) Theory (Paper 2) booklet, Part 2 of 2.

Q399706/21/O/N/24original Q4Structured · 30 marks
Question 4 from 9706/21/O/N/24

Worked solution

(a)

(i) A cost centre is a production location where costs may be attributed to cost units. [1]

(ii) A cost unit is a unit of production that absorbs the cost centre's overhead costs. [1]

(iii) A direct cost is one that can be specifically associated with the manufacture of one unit of production. [1]

(iv) An indirect cost is one that cannot economically be specifically associated with the manufacture of one unit of production. [1]

(b)

Bases: light and heat by floor area (10 000 square metres in total); production supervisors' wages by number of employees in the two production departments (6 and 10); canteen by number of employees (20 in total); stores by stores requisitions (3 600 and 5 400).

DetailsTotal $Machining $Finishing $Stores $Canteen $
Allocated overheads512 100195 200234 70066 40015 800
Light and heat12 8003 8406 4001 920640 [1]
Production supervisors' wages42 00015 75026 250–– [1]
Total overheads566 900214 790267 35068 32016 440
Reapportion Canteen4 9328 2203 288(16 440) [1]
Subtotal219 722275 57071 608–
Reapportion Stores28 64342 965(71 608)– [1]
Total248 365318 535–– [2]

(c)

Rate = overheads ÷ hours, using own figures from (b). Machining uses machine hours (28 900); Finishing uses direct labour hours (18 500).

Machining = $248 365 ÷ 28 900 = $8.59 per machine hour [1]

Finishing = $318 535 ÷ 18 500 = $17.22 per direct labour hour [1]

(d)

Overhead absorbed = actual hours × rate; compare with actual overheads.

Machining: $8.59 × 26 880 = $230 899. $230 899 − $249 200 = $18 301 [1]

under absorbed [1]

Finishing: $17.22 × 18 650 = $321 153. $321 153 − $320 400 = $753 [1]

over absorbed [1]

(e)(i)

(i) Budgeted hourly direct labour rate = budgeted labour cost ÷ budgeted direct labour hours.

Machining = $127 270 ÷ 14 300 hours = $8.90 per hour [1]

Finishing = $183 150 ÷ 18 500 hours = $9.90 per hour [1]

(e)(ii)

Gross margin 40% means selling price = cost ÷ 0.60. Cost for one unit first, then 12 units.

Cost per unitWorking$
Direct material4 metres × $3.8515.40 [1]
Direct labour, Machining0.75 × $8.906.68 [1]
Direct labour, Finishing1.5 × $9.9014.85 [1]
Overheads, Machining0.5 × $8.594.30 [1]
Overheads, Finishing1 × $17.2217.22 [1]
Total cost58.45 [1]
Profit margin (40% of price)$97.42 − $58.4538.97
Price per unit$58.45 ÷ 0.6097.42
Quotation12 × $97.421 169.04 [1]

(f)

Give financial and non-financial points (any four in all), then your advice.

Financial: Alberto will still make a profit on the work. After the 20% discount the price is $1 169.04 × 0.80 = $935.23, against costs of $701.40. [1]

Financial: the margin is then 25%, which fails to reach the target margin of 40%. [1]

Non-financial: the work uses spare capacity and gives employees less down-time, a positive effect. [1]

Non-financial: existing customers may be upset if they find out about the discount. [1]

Also accepted: overheads will be under absorbed because the price is lower.

Advice: accept the terms, because the factory has spare capacity and the work still makes a profit, but the lower margin should be kept to this order only. [1]

KEY IDEAAbsorb overheads with a rate per hour, then price a job by adding the profit margin to total cost.
TOTAL 30 marks

Official mark scheme

Mark scheme for 9706/21/O/N/24 question 4
VIDEO
▶ Starts at Q4 (1:55:52)

Starts at Q4 (1:55:52) · by Sir Waleed Khanzada. Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes; marks are shown in grey. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.