Cambridge O Level Accounting 7707 · 5.5 Manufacturing accounts

Q165 · 7707/13/O/N/22 Q29

Worked solution from the Preparation of financial statements MCQ booklet.

Q1657707/13/O/N/22original Q29Multiple choice
Question 29 from 7707/13/O/N/22

Worked solution

The question asks for the cost of production of finished goods in a manufacturing account.

Prime cost + factory overheads = $35 000 + $17 000 = $52 000

Add opening work in progress and take off closing work in progress: $52 000 + $1 400 − $2 300 = $51 100

So the answer is B.

A forgets the opening work in progress. D adds the closing and takes off the opening, the wrong way round. C ignores the work in progress.

KEY IDEACost of production = prime cost + factory overheads + opening work in progress − closing work in progress.
ANSWER B