Worked solution from the Cost and management accounting (AS Level) MCQ booklet.
The question asks for the revenue needed for the target profit after the cost increases.
New fixed costs = $2 000 + $500 = $2 500. New variable cost = $15 + $5 = $20 per unit.
Contribution per unit = $40 − $20 = $20.
Units needed = ($2 500 + $3 000) ÷ $20 = 275 units.
Revenue = 275 × $40 = $11 000.
So the answer is D.
A, B and C use old costs or leave out the cost increases.
▶ Starts at Q29 (56:17)
Starts at Q29 (56:17) · by Study with Prashna. Tap the picture to open it on YouTube.
Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.