The question asks for the break-even point in units. First split the semi-variable overhead into its variable and fixed parts.

Variable overhead per unit = ($40 000 − $32 000) ÷ (40 000 − 20 000) = $8 000 ÷ 20 000 = $0.40

Fixed overhead = $32 000 − (20 000 × $0.40) = $32 000 − $8 000 = $24 000

Variable cost per unit = $2.20 + $4.20 + $0.40 = $6.80

Contribution per unit = $10.80 − $6.80 = $4.00

Break-even point = fixed costs ÷ contribution per unit = $24 000 ÷ $4.00 = 6 000 units

So the answer is B.

A uses fixed costs of $24 000 but a contribution of $4.40, leaving out the variable overhead. C uses $32 000 with $4.40. D uses $32 000 fixed costs with the correct contribution.

KEY IDEASplit a semi-variable cost into fixed and variable parts before finding break-even.
ANSWER B
VIDEO
▶ Starts at Q29 (39:09)

Starts at Q29 (39:09) · by Study with Prashna. Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.