Cambridge A2 Level Business 9609 · 9.3 Operations strategy

Q27 · 9609/33/O/N/21 Q3

Worked solution from the Operations management Theory (Paper 3) booklet, Part 3 of 3.

Q279609/33/O/N/21original Q3Structured · 16 marks
Question 3 from 9609/33/O/N/21

Worked solution

Evaluate means: give points for and against, then reach a judgement that answers the question (is lean production enough to improve efficiency?).

Knowledge: lean production is a set of techniques that aim to eliminate or minimise waste while keeping high quality. Techniques include Kaizen (continuous improvement), JIT inventory management, total quality management (TQM), cell production and quality circles. Efficiency means getting the most output from a given quantity of inputs.

Application: WSC imports raw spices that lose flavour if inventory is kept too long, needs a large amount of storage space, and has high wastage of raw materials. Labour turnover is rising and employees have little involvement, although the production workers are highly skilled and can taste small differences. WSC buys from growers in many countries, so its supply chain is long.

For (benefits): Kaizen groups gather ideas from employees, so productivity rises and efficiency improves. More involvement may also motivate staff, so labour turnover falls (a current problem at WSC).

TQM makes quality everyone's responsibility, so things are done right first time. Wastage of spices falls, so more output comes from the same inputs.

Multi-skilled, flexible workers mean less labour is needed as an input. JIT cuts the large storage space needed and cuts wastage, so costs fall and efficiency rises.

Against (problems): training costs time and money in the short term, and output may fall during the change.

Lean production is more demanding of employees, which can cause stress and dissatisfaction, so productivity may fall and labour turnover rise.

With JIT, variations in demand or supplier problems can cause stock-outs, so customers are dissatisfied.

Evaluation: JIT needs excellent supplier relationships, which is hard with suppliers in many countries and long distances. How far lean production works also depends on managers' ability to engage employees, for example in introducing TQM.

So lean production helps but is not sufficient on its own. Investing in capital equipment may also be needed to raise efficiency, for example for the ready meals project. Other methods may matter more, so WSC should combine lean production with other changes.

This earns the top level for knowledge: it gives two relevant points, the meaning of lean production and of efficiency. [2]

This earns the top level for application: it uses two details about WSC. [2]

This reaches the top level for analysis: good use of theory and reasoned argument, with benefits and problems explained as chains. [6]

This reaches the top level for evaluation: good judgement, with a supported conclusion on whether lean production is enough. [6]

KEY IDEALean production cuts waste and raises efficiency, but it depends on suppliers and employees and is rarely enough on its own.
TOTAL 16 marks

Official mark scheme

Mark scheme for 9609/33/O/N/21 question 3
VIDEO
▶ Topic lesson

A lesson on this topic · by Saifullah Ajaz . Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes; marks are shown in grey. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.