9706/32/O/N/20 question 6: worked solution (October/November 2020, paper 32)

Show as plain text

Cambridge A2 Level Accounting 9706 · 4.2 Standard costing Worked solution from the Cost and management accounting (A Level) Theory (Paper 3) booklet, Part 2 of 4. Q21 9706/32/O/N/20 original Q6 Structured · 25 marks Worked solution (a)(i) Standard kilos for actual output = 14 000 × 2 = 28 000 kilos [1] Usage variance 22 800 (F) ÷ $6 = 3 800 kilos saved [1] Kilos used = 28 000 − 3 800 = 24 200 kilos [1] (a)(ii) Price variance ÷ kilos used = $36 300 ÷ 24 200 = $1.50 per kilo more than standard [1] Standard price $6 + $1.50 [1] = $7.50 per kilo [1] (a)(iii) Labour rate variance = actual hours × (actual rate − standard rate) = 53 200 × ($10.40 − $10) = $21 280 [1] The variance is Adverse (actual rate is higher). [1] (a)(iv) Standard hours for actual output = 14 000 × 4 = 56 000. Efficiency variance = (56 000 − 53 200) × $10 = $28 000 [1] The variance is Favourable (fewer hours used). [1] (a)(v) Fixed overheads: budget 15 000 × 4 × $3.50 = $210 000; less $10 000 favourable expenditure variance = $200 000. Details $ Sales (14 000 × $104) 1 456 000 [1] Direct materials (24 200 × $7.50) (181 500) [1] Direct labour (53 200 × $10.40) (553 280) [1] Fixed overheads (200 000) [1] Actual profit 521 220 [1] (b) Details $ Profit from flexed budget 476 000 Sales price variance (14 000 × $4) 56 000 [1] Materials price variance (36 300) Materials usage variance 22 800 [1] Labour rate variance (21 280) [1] Labour efficiency variance 28 000 [1] Fixed overhead expenditure variance 10 000 Fixed overhead volume variance (14 000) [1] Actual profit 521 220 [1] (c) Write: fixed overhead capacity variance [1] and fixed overhead efficiency variance . [1] (d) (i) Materials price: the price of materials increased , or a higher grade was bought from a more expensive supplier. [1] (ii) Materials usage: less material was used , for example lower wastage or improved quality. [1] KEY IDEA Variances explain the gap between budgeted and actual profit, one cost at a time, with adverse ones reducing profit. TOTAL 25 marks Official mark scheme VIDEO ▶ Whole paper Video solution of the whole paper · by IGCSE / AS LEVEL / A LEVEL MATHS AND ACCOUNTS. Tap the picture to open it on YouTube.