Cambridge A2 Level Business 9609 · 6.2 Business strategy

Q75 · 9609/33/M/J/22 Q7

Worked solution from the Business and its environment Theory (Paper 3) booklet, Part 2 of 2.

Q759609/33/M/J/22original Q7Structured · 20 marks
Question 7 from 9609/33/M/J/22

Worked solution

Answer

Contingency planning means preparing a business's resources for unlikely events that could badly damage it (it is also called scenario or business continuity planning). A strategy is a long-term plan to reach objectives. Diversification means moving into new products or markets. TK is choosing between Option 1, a chain of luxury restaurants, and Option 2, taking over a small premium snack manufacturer.

Application to the risks: both options bring major risks. Food contamination could hit a restaurant or the snack factory. Failure of equipment could spoil stored food in either option. In Option 2, a failure of snack supplies would stop TK selling its new product. In Option 1, a fire in a restaurant or a cyber attack on the booking system could close it. TK has already seen that a recession in 2020 kept people at home and away from restaurants.

Benefits (analysis): a plan lets TK respond more quickly when something goes wrong. The public relations response is then much more likely to be quick and suitable, so managers can deal with the media and with worried customers and employees. Clear communication of what TK will do, by when and how, reduces bad publicity and the loss of customer loyalty. This matters because TK's reputation rests on quality, and it never meets its customers face to face. Crisis management becomes easier, so sales are less likely to fall. TK is also less dependent on which employees happen to be present, which helps because each kitchen runs under its own manager. Reassuring customers and staff that their interests are considered protects the money TK must invest ($4m for Option 1, $2.5m for Option 2). Recognising the major risks may even reduce the chance of them happening.

Limitations (analysis): planning is expensive and time consuming. TK must write the plans and train staff for each possible event. Markets are dynamic (changing food trends, new competitors), so plans need regular updates, which means ongoing time and cost. Disruptive events will still happen, and TK cannot plan for every possible event.

Evaluation: contingency planning is important, but it is only one element of the business planning needed to carry out a diversification strategy. It may be better to avoid major disruptions in the first place, for example by good food safety checks, than to plan what to do when they happen. The cost of planning must be balanced against the possible cost of not planning: a closed restaurant or a contaminated product could damage the whole TK brand. TK should plan for the most likely and most damaging events, such as food contamination, equipment failure and cyber attack, and test those plans, rather than spend time on every possibility. It is impossible to plan for all eventualities. The importance may be greater for Option 1, which has more exposure (fire, lockdowns, booking system). It is still important for Option 2, because the takeover depends on supplies and food safety.

Conclusion: contingency planning is very important but not enough on its own. TK should plan for the main risks of whichever option it chooses, update the plans regularly, and combine them with other strategic planning, because the benefit of faster response and protected reputation outweighs the cost.

This earns the top band for knowledge: it defines contingency planning, strategy and diversification accurately. [2]

It earns the top band for application: it uses specific risks for both options (contamination, equipment failure, snack supplies, fire, recession, cyber attack). [2]

It reaches the top level for analysis: developed points on benefits (speed, PR, communication, crisis management) and on cost, time and updating, all linked to TK. [8]

It reaches the top level for evaluation: justified judgement on the extent of importance, with balance (one element of planning, prevention, cost against benefit, impossible to plan for everything) and a conclusion. [8]

KEY IDEAContingency planning protects a diversifying business from unlikely but damaging events, but it costs time and money and cannot cover everything, so plan for the biggest risks and keep the plans up to date.
TOTAL 20 marks

Official mark scheme

Mark scheme for 9609/33/M/J/22 question 7