Cambridge O Level Business Studies 7115 · 4.1 Production of goods and services

Q16 · 7115/12/O/N/23 Q2

Worked solution from the Operations management Theory (Paper 1) booklet, Part 1 of 4.

Q167115/12/O/N/23original Q2Structured · 20 marks
Question 2 from 7115/12/O/N/23

Worked solution

(a)

Write any two ways (one mark each).

Way 1: pollution (for example air or noise pollution, or emission of greenhouse gases). [1]

Way 2: use of energy or natural resources (for example using fossil fuels, or using up land and raw materials). [1]

(b)

Write any two ways (one mark each).

Way 1: reduce waste. [1]

Way 2: recycle or reuse materials (or use renewable energy). [1]

(c)

Outline means give the main point only. Name the economy of scale, then link it to TBX.

Economy of scale 1: purchasing economy (knowledge), when buying the large amounts of iron ore it needs (application). [2]

Economy of scale 2: technical economy (knowledge), using large machines to make its steel (application). [2]

(Other creditable ones: managerial, financial, marketing economies.)

(d)

Explain means: give the problem, apply it to TBX, then say what it leads to.

Problem 1: it ties up working capital (knowledge) in iron ore and steel (application). [2]

This could lead to cash flow or liquidity problems, so TBX may find it hard to pay suppliers (analysis). [1]

Problem 2: storage space is needed (knowledge). Large amounts of steel need a lot of space (application). [2]

This increases fixed costs, so TBX's expenses rise (analysis). [1]

(Other creditable problem: risk of damage, theft or rust, which leads to higher costs.)

(e)

This is a general question, so there are no application marks.

For quality control: it tries to find faults before the product reaches the customer (knowledge), which helps to keep the business's reputation (development). [2]

It does not stop production while the checks are made (knowledge), so some output is still available (development). [2]

Against: inspectors must be recruited, which raises labour costs. Errors are found only at the end, so the business cannot see where the fault happened, which can increase wastage. Quality assurance spots mistakes earlier, so less time and money is spent on reworking, but all employees need training, which increases costs.

Decision: write whether you think quality control is the best method, and why. For example: quality control is not the best, because quality assurance spots mistakes sooner, so fewer resources are wasted. [1]

The money saved should help cover the extra cost of training. (Choosing quality control is also creditable if you explain that workers need no extra training, so costs do not rise.) [1]

KEY IDEAHolding a lot of inventory ties up money and space, and quality can be checked at the end (control) or at every stage (assurance).
TOTAL 20 marks

Official mark scheme

Mark scheme for 7115/12/O/N/23 question 2
VIDEO
▶ Whole paper

Video solution of the whole paper · by Economics by Abdul Hadi. Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes; marks are shown in grey. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.