9706/13/O/N/24 question 24: worked solution (October/November 2024, paper 13)
Show as plain textHide plain text
Cambridge AS Level Accounting 9706 · 2.1 Costs and cost behaviour Worked solution from the Cost and management accounting (AS Level) MCQ booklet. Q77 9706/13/O/N/24 original Q24 Multiple choice Worked solution The question asks for the bonus for week 25. Time allowed for 250 units = 250 ÷ 200 × 40 hours = 50 hours. Hours saved = 50 − 44 = 6 hours. Bonus = 6 × $10 = $60 . So the answer is D . A , B and C use the wrong hours saved; for example $50 would be 5 hours saved. The time allowed must be based on the 250 units made. KEY IDEA Time allowed is based on the output made; bonus = hours saved × rate. ANSWER D VIDEO ▶ Starts at Q24 (44:26) Starts at Q24 (44:26) · by Study with Prashna. Tap the picture to open it on YouTube.