Worked solution from the Cost and management accounting (AS Level) Theory (Paper 2) booklet, Part 2 of 2.
Write: allocation is charging overheads (costs) to a specific cost centre [1]
where the overheads are clearly identified with that cost centre. [1]
Write: apportionment is charging overheads that cannot be clearly identified with one cost centre [1]
to the cost centres on a suitable (fair) basis. [1]
Write one benefit: it is useful for working out a selling price (or: it avoids separating costs into fixed and variable). [1]
Write one limitation: it is not useful for short-term decision making (or: it is not suitable for monitoring managers' performance). [1]
Reapportion Maintenance first ($26 700: 60% Assembly, 30% Finishing, 10% Stores), then Stores ($21 870: 75% Assembly, 25% Finishing).
| Details | Assembly $ | Finishing $ | Stores $ | Maintenance $ |
|---|---|---|---|---|
| Total overhead costs | 275 000 | 103 200 | 19 200 | 26 700 |
| Maintenance (60%, 30%, 10%) | 16 020 | 8 010 | 2 670 | (26 700) [1] |
| Subtotal | 291 020 | 111 210 | 21 870 | – |
| Stores (75%, 25%) | 16 403 | 5 467 | (21 870) | – [1] |
| Total | 307 423 | 116 677 | – | – [1] |
(The exact figures are $307 422.50 and $116 677.50, used in (e).)
Overhead absorption rate = overheads ÷ budgeted hours. For the Assembly department use machine hours.
= $307 422.50 ÷ 1 430 = $214.98 (using own figure from (d)) [1]
The unit is per machine hour. [1]
For the Finishing department use labour hours.
= $116 677.50 ÷ 840 = $138.90 (using own figure from (d)) [1]
The unit is per labour hour. [1]
Overheads absorbed = actual machine hours × rate = 1 310 × $214.98 = $281 623.80 [1]
Actual overheads $285 400 − absorbed $281 623.80 = $3 776.20 [1]
Actual is more than absorbed, so the overheads are under-absorbed by $3 776.20. [1]
Option A: contribution per unit of X = $24 − $6 − $9 = $9
Product X units = 8 000 + 4 000 (labour hours moved from Z) = 12 000 units. Contribution = 12 000 × $9 = $108 000 [2]
Less fixed costs ($40 000 for X + $24 000 for Z + $3 000 retraining) = $67 000 [1]
Profit = $108 000 − $67 000 = $41 000 [1]
Option B: new X price = $24 × 95% = $22.80; variable cost = $6 + $9 = $15; contribution = $7.80
Product X: 8 000 × $7.80 = $62 400 − fixed costs $40 000 = $22 400 [1]
Product Z: contribution $30 − $9 − $9 = $12; 4 000 × $12 = $48 000 − fixed costs $24 000 = $24 000 [1]
Total profit = $22 400 + $24 000 = $46 400 [1]
Option A (any three points):
It makes sure the major customer keeps ordering in future. [1]
It makes less profit ($41 000 against $46 400). [1]
How will customers for Product Z react: will their future orders be lost? [1]
(Also: can the training be done in time without losing production?)
Option B (any three points):
It makes more profit ($46 400). [1]
It lets the orders of other regular customers be met. [1]
Will the price cut really give the sales of Product X needed, now and in future? [1]
(Also: the danger of losing the major customer, and how competitors may react.)
Decision: write a clear choice of option, using the points above. [1]
▶ Whole paper
Video solution of the whole paper · by Karachians Academy. Tap the picture to open it on YouTube.
Solutions follow the official Cambridge mark schemes; marks are shown in grey. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.