Cambridge AS Level Accounting 9706 · 2.1 Costs and cost behaviour

Q83 · 9706/12/M/J/25 Q24

Worked solution from the Cost and management accounting (AS Level) MCQ booklet.

Q839706/12/M/J/25original Q24Multiple choice
Question 24 from 9706/12/M/J/25

Worked solution

The question asks for the total fixed costs in July. Variable cost per unit stayed the same, and fixed costs rose by $1 000 in July.

Total cost change = $86 000 − $76 000 = $10 000

The extra $10 000 = extra variable cost + the $1 000 rise in fixed cost, so extra variable cost = $9 000.

Extra units = 10 000 − 8 000 = 2 000, so variable cost per unit = $9 000 ÷ 2 000 = $4.50

June fixed costs = $76 000 − (8 000 × $4.50) = $76 000 − $36 000 = $40 000

July fixed costs = $40 000 + $1 000 = $41 000

So the answer is C.

B ($36 000) is June's variable cost. A is not from this working. D ($76 000) is June's total cost.

KEY IDEARemove the fixed-cost rise from the cost change before finding the variable cost per unit.
ANSWER C
VIDEO
▶ Starts at Q24 (40:38)

Starts at Q24 (40:38) · by Study with Prashna. Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.