The question asks for the total fixed costs in July. Variable cost per unit stayed the same, and fixed costs rose by $1 000 in July.
Total cost change = $86 000 − $76 000 = $10 000
The extra $10 000 = extra variable cost + the $1 000 rise in fixed cost, so extra variable cost = $9 000.
Extra units = 10 000 − 8 000 = 2 000, so variable cost per unit = $9 000 ÷ 2 000 = $4.50
June fixed costs = $76 000 − (8 000 × $4.50) = $76 000 − $36 000 = $40 000
July fixed costs = $40 000 + $1 000 = $41 000
So the answer is C.
B ($36 000) is June's variable cost. A is not from this working. D ($76 000) is June's total cost.