Worked solution from the Cost and management accounting (A Level) Theory (Paper 4) booklet, Part 2 of 4.
Formula: actual selling price = standard price − adverse sales price variance per unit (units sold were 11 000, as the sales volume variance is nil).
Sales price variance per unit = $55 000 ÷ 11 000 = $5 adverse [1]
Actual unit selling price = $210 − $5 = $205 [1]
Add up the cost variances (the two material variances are favourable, labour efficiency is adverse), then find the extra price per unit:
Net adverse cost variances = $57 750 − $4 290 − $8 360 = $45 100 [1]
Extra price per unit = $45 100 ÷ 11 000 = $4.10 [1]
Unit selling price needed = $210 + $4.10 = $214.10 [1]
(Own figure is allowed. Alternative: ($55 000 + $57 750 − $4 290 − $8 360) ÷ 11 000 = $9.10, then $205 + $9.10 = $214.10.)
Formula: material usage variance = (standard quantity − actual quantity) × standard price, so quantity saved = variance ÷ standard price.
Kilos saved = $8 360 ÷ $7.60 = 1 100 kilos [1]
Standard kilos for actual output = 11 000 units × 4 kilos = 44 000 kilos [1]
Actual kilos used = 44 000 − 1 100 = 42 900 kilos [1]
Formula: material price variance = (standard price − actual price) × actual quantity, so price saved per kilo = variance ÷ actual quantity.
Price saved per kilo = $4 290 ÷ 42 900 = $0.10 favourable [1]
Actual price per kilo = $7.60 − $0.10 = $7.50 [1]
Formula: labour efficiency variance = (standard hours − actual hours) × standard rate, so hours over-used = variance ÷ standard rate. The labour rate variance is nil, so the actual rate is $10.50.
Extra hours per unit = $57 750 ÷ ($10.50 × 11 000 units) [1]
= 0.5 hours per unit [1]
Actual hours per unit = 3 + 0.5 = 3.5 hours [1]
Write: a flexible budget statement. [1]
Suggest means give four reasons. Write any four of these:
Standard costs help cost control and cost reduction. [1]
They give a benchmark to compare actual results against. [1]
They help with decision making. [1]
They motivate staff. [1]
(Other accepted points: they help estimate future materials and labour needs; they simplify setting selling prices; they simplify inventory valuation; they help co-ordinate the different functions when the standards are set.)
Advise means give points for and against, then a decision. Write three points for using spreadsheets (any three):
Arithmetical errors should be avoided. [1]
Speed of calculation will improve, and there is automatic recalculation if one variable is changed. [1]
It lets managers ask 'what if' questions. [1]
(Other accepted points: security can be improved with passwords; information is easily sent between offices or departments; multi-user applications may be available; sort or select functions are useful.)
Now write three points against (any three):
Some staff may not be familiar with the software. [1]
The budgets will only be as good as the estimates made. [1]
Security of data may be compromised, errors in data entry can be made, or incorrect formulae can be used. [1]
Decision: write that the directors should use spreadsheets (or should not), supported by a comment, for example that the speed and accuracy gains outweigh the risks listed. [1]