Cambridge A2 Level Business 9609 · 9.3 Operations strategy

Q45 · 9609/32/O/N/24 Q5

Worked solution from the Operations management Theory (Paper 3) booklet, Part 3 of 3.

Q459609/32/O/N/24original Q5Structured · 12 marks
Question 5 from 9609/32/O/N/24

Worked solution

(a)

Knowledge. Critical path analysis (CPA) uses a network diagram to show every activity, the critical path, the floats and the minimum project time. As a planning tool it shows start times, helps manage resources, lets managers monitor progress, and shows how serious a delay is so that corrective action can be taken. Its limits: it is only as good as the data put in, planning costs money, and it does not by itself ensure good management.

Application. HCC's Operations Manager has produced a CPA for the new canteen and rest room, giving a six-week minimum time. Building work will disrupt production and Abeba is worried that any delay will be costly. CPA could also be used for other projects, such as exporting to country K, where HCC wants to enter the market by January 2025 (the Wonder Stove was launched on schedule).

Analysis. CPA helps HCC manage resources so they are available when needed, which cuts the cost of the work and supports HCC's social objectives. Showing which tasks are critical means they are finished on time, so disruption to production is kept small and the cost of the improvements is lower. Customers can be told of any effect on orders, which avoids dissatisfaction and lost sales. Entering the export market needs careful planning so that products reach customers on time, which increases sales.

Evaluation. Overall CPA is very useful to HCC, especially for a costly project where delay would cost money. But its usefulness depends on the accuracy of the data and on whether the Operations Manager can produce an accurate CPA for the building work. The CPA must also be interpreted, work must keep to the plan, and HCC should check progress constantly before and after the work starts. Without CPA, HCC could fall behind schedule, disappoint customers and damage its brand image, so I judge it worthwhile provided it is accurate and monitored.

This earns the top level for knowledge: developed knowledge of the key terms and factors. [2]

It earns the top level for application: developed application, using the case facts at least twice. [2]

It earns the top level for analysis: developed chains of cause, effect and consequence. [2]

It reaches the top level for evaluation (Level 3): a developed judgement in context that balances the key arguments. [6]

KEY IDEACritical path analysis shows the minimum time and the critical tasks of a project, but it is only as good as the data and the monitoring behind it.
TOTAL 12 marks

Official mark scheme

Mark scheme for 9609/32/O/N/24 question 5