The question asks for over or under absorbed overheads. The rate is based on budgeted figures. Under absorption means the overhead absorbed is less than the actual overhead.

Absorption rate = budgeted overhead ÷ budgeted direct labour hours

= $242 880 ÷ 96 000 = $2.53 per hour

Overhead absorbed = actual hours × rate = 97 600 × $2.53 = $246 928

Actual overhead = $253 760

Difference = $253 760 − $246 928 = $6 832

Absorbed is less than actual, so the overhead is under absorbed by $6 832.

So the answer is B.

A and C say over absorbed, but the overhead is under absorbed. C and D use $10 880, which is actual overhead less budgeted overhead ($253 760 − $242 880) and ignores the extra hours worked.

KEY IDEAUnder or over absorption = actual overhead − (actual hours × budgeted rate).
ANSWER B
VIDEO
▶ Starts at Q23 (33:59)

Starts at Q23 (33:59) · by Study with Prashna. Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.