Question 26 from 9706/12/M/J/24

Worked solution

The question asks which two factors mean fixed overheads are under-absorbed. Under-absorption means the overheads absorbed are less than the overheads incurred.

Fixed overheads are absorbed using a rate based on budgeted hours or output. If the actual hours worked are less than the budget (factor 1), fewer hours carry the rate, so less is absorbed. If the actual output is less than the budget (factor 3), the same happens.

Factors 2 and 4 would mean more is absorbed than budgeted, which gives over-absorption.

Statements 1 and 3 are the correct pair.

So the answer is A.

B, C and D each include a factor that causes over-absorption.

KEY IDEAFixed overheads are under-absorbed when actual hours or output are lower than budgeted.
ANSWER A
VIDEO
▶ Starts at Q26 (35:30)

Starts at Q26 (35:30) · by Study with Prashna. Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.