Worked solution from the The normal distribution Paper 5 Probability & Statistics 1 booklet, Part 1 of 2.
Standardise 4.2 using Z = X − μσ with μ = 3.5 and σ = 0.9.
P(X > 4.2) = P(Z > 4.2 − 3.50.9) = P(Z > 0.7778) [1]
Use the table: P(Z > 0.7778) = 1 − Φ(0.7778) = 1 − 0.7818 [1]
So the probability is 0.218. [1]
90% of days are above t, so the area below t is 0.1. That puts t below the mean, so z is negative.
Φ−1(0.1) gives z = −1.282 [1]
t − 3.50.9 = −1.282 [1]
t = 3.5 − 1.282 × 0.9 = 2.3462, so t = 2.35 hours. [1]
By symmetry, 2.8 and 4.2 are each 0.7 from the mean, so the area between them is 1 − 2 × P(X > 4.2).
P(2.8 < X < 4.2) = 1 − 2 × 0.2182 = 0.5636 [1]
Expected number of days = 365 × 0.5636 = 205.7 [1]
So about 205 days (206 is also accepted). [1]