Cambridge AS Level Accounting 9706 · 2.2 Traditional costing methods

Q329 · 9706/12/O/N/25 Q25

Worked solution from the Cost and management accounting (AS Level) MCQ booklet.

Q3299706/12/O/N/25original Q25Multiple choice
Question 25 from 9706/12/O/N/25

Worked solution

The question asks which overhead absorption rate would have been used. A predetermined rate uses budgeted figures. A cutting department works mainly with machines, so machine hours are the sensible basis.

Budgeted overheads = $40 000

Budgeted machine hours = 2 800, so rate = $40 000 ÷ 2 800 = $14.29 per machine hour

The actual figures ($44 000, 2 700, 2 900) are not used in setting a predetermined rate.

So the answer is A.

B and C use labour hours, which suit a cutting department less well than machine hours. D uses the actual overhead and actual machine hours ($44 000 ÷ 2 700), which a predetermined rate does not use.

KEY IDEAA predetermined rate = budgeted overheads ÷ budgeted hours; actual figures are not used.
ANSWER A
VIDEO
▶ Starts at Q25 (41:56)

Starts at Q25 (41:56) · by Study with Prashna. Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.