Worked solution from the Cost and management accounting (AS Level) MCQ booklet.
The question asks for the actual overheads in July.
Overheads are absorbed on the machine hours actually used: 8 500 × $15 = $127 500.
The overheads were under-absorbed by $16 500, so actual overheads are higher than absorbed.
Actual overheads = $127 500 + $16 500 = $144 000.
So the answer is D.
A, B and C come from using budgeted hours ($120 000) or subtracting the under-absorption.
▶ Starts at Q25 (43:02)
Starts at Q25 (43:02) · by Study with Prashna. Tap the picture to open it on YouTube.