Worked solution from the Cost and management accounting (AS Level) MCQ booklet.
The question asks for the total fixed cost for 100 000 units. The cost has an ordinary fixed part and a rent for machines, which is a stepped cost because each machine covers 60 000 units.
Variable cost per unit = ($660 000 − $510 000) ÷ (120 000 − 90 000) = $150 000 ÷ 30 000 = $5
Fixed cost (excluding rent) = $510 000 − (90 000 × $5) = $510 000 − $450 000 = $60 000
Both 90 000 and 120 000 units need 2 machines, so the machine rental is the same at both levels and the working above is correct.
For 100 000 units, 2 machines are needed (one machine covers only 60 000 units): rent = 2 × $12 000 = $24 000
Total fixed cost = $60 000 + $24 000 = $84 000
So the answer is B.
C ($150 000) is only the rise in total cost between the two levels. A and D do not come from this working.
▶ Starts at Q23 (47:20)
Starts at Q23 (47:20) · by Study with Prashna. Tap the picture to open it on YouTube.
Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.