Cambridge A2 Level Accounting 9706 · 4.2 Standard costing

Q20 · 9706/33/M/J/20 Q5

Worked solution from the Cost and management accounting (A Level) Theory (Paper 3) booklet, Part 2 of 4.

Q209706/33/M/J/20original Q5Structured · 25 marks
Question 5 from 9706/33/M/J/20

Worked solution

(a)

Standard costs per unit: materials 5 × $4 = $20; labour 3 × $12 = $36.

Fixed overheads per unit = ($42 000 ÷ 12 000 hours) × 3 hours = $10.50 [1]

Budgeted profit = ($82 − $20 − $36 − $10.50) × 4 000 units

= $15.50 × 4 000 = $62 000 [1]

(b)

Actual profit = sales − actual costs

Sales = 4 300 × $80 = $344 000

Costs = $95 718 + $150 500 + $43 600 = $289 818

Actual profit = $344 000 − $289 818 = $54 182 [1]

(c)

Standard profit margin per unit = $82 − $20 − $36 − $10.50 = $15.50.

(i) Sales price variance = ($82 − $80) × 4 300 = $8 600 adverse [2]

(ii) Sales volume variance = (4 300 − 4 000) × $15.50 = $4 650 favourable [2]

(iii) Actual labour rate = $150 500 ÷ 12 040 = $12.50. Labour rate variance = ($12.50 − $12) × 12 040 = $6 020 adverse [2]

(iv) Labour efficiency variance = (12 040 − 4 300 × 3) × $12 = (12 040 − 12 900) × $12 = $10 320 favourable [2]

(v) Fixed overhead expenditure variance = $43 600 − $42 000 = $1 600 adverse [2]

(vi) Fixed overhead volume variance = (4 300 − 4 000) × $10.50 = $3 150 favourable [2]

(d)

Start with the budgeted profit from (a), add favourable variances and take off adverse variances.

ReconciliationFavourable $Adverse $$
Budgeted profit62 000
Sales price variance8 600
Sales volume variance4 650[1]
Material price variance4 558
Material usage variance5 160[1]
Labour rate variance6 020
Labour efficiency variance10 320[1]
Fixed overhead expenditure variance1 600
Fixed overhead volume variance3 150[1]
Total variances18 120(25 938)(7 818)
Actual profit54 182 [1]

(e)

Decision: write whether to change; the decision earns 1 mark and up to 4 marks for justification.

The adverse materials price variance shows the current price is higher than expected. [1]

The adverse usage variance suggests poor quality materials led to wastage, and better quality could reduce wastage. [1]

But no trade discount makes the new materials more expensive, and the higher price may outweigh the better usage. [1]

Better quality may attract new customers and increase sales and profit, but it is uncertain whether the new supplier is reliable. [1]

Decision: for example, change to the new supplier, as the better quality should cut the wastage shown by the usage variance (a justified decision to stay is also credited). [1]

KEY IDEAReconcile budgeted profit to actual profit by adding favourable and subtracting adverse variances.
TOTAL 25 marks

Official mark scheme

Mark scheme for 9706/33/M/J/20 question 5
VIDEO
▶ Topic lesson

A lesson on this topic · by Edex World. Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes; marks are shown in grey. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.