Worked solution from the Operations management Theory (Paper 3) booklet, Part 1 of 3.
EMV = (probability × outcome) added up for each forecast, then take away the cost of the option.
Optimistic: $9.0m × 0.7 = $6.3m [1]
Pessimistic: $6.0m × 0.3 = $1.8m (together: $6.3m + $1.8m = $8.1m) [1]
Take off the cost of the new factory: $8.1m − $5.5m [1]
EMV = $2.6m (write the $ and the m: without them only 3 marks) [1]
Knowledge. A decision tree compares options by weighting each possible outcome by its probability, so it allows for uncertainty and risk. The decision also depends on TC's objectives, the finance available and its cost, profit, risk, and the market in country M.
Application. TC makes premium boxed chocolates. Option B has the highest EMV: $2.6m against $0.9m for option A and $0.84m for option C. It also has the higher chance of the optimistic forecast (0.7 against 0.6), and a pessimistic outcome of $6.0m still beats its $5.5m cost. The directors want to increase sales to country M.
Analysis. The new factory gives more capacity, so TC can sell more in country M and may raise profit. But it is the most expensive option, nearly eight times option A at $0.7m. The interest rate in country R is high, so if TC has to borrow, the cost is high and TC's liquidity (a director concern) could get worse. TC's plans for AI, a new product range and TQM also need money. A new factory needs trained staff, a site and permissions, so it will take longer to produce profit, and there is greater risk if sales are below forecast.
Evaluation. On the numbers alone, option B is the wise choice, because it has the highest EMV and the consultant recommends it. But the data is only an estimate by a consultant, and EMVs are averages that may never actually happen. So the answer depends on whether the probabilities are accurate, whether TC can find the $5.5m without damaging liquidity, and whether it can get employees, a site and permissions. TC has not shown any research into the market in country M, so it should research this first, or perhaps try the cheaper new marketing strategy before building. I would recommend option B only if the research supports the forecasts and the finance can be found; otherwise a cheaper option is safer.
This earns the top level for knowledge: developed knowledge of the key terms and factors. [2]
It earns the top level for application: developed application, using the case facts at least twice. [2]
It earns the top level for analysis: developed chains of cause, effect and consequence. [2]
It reaches the top level for evaluation (Level 3): a developed judgement in context that balances the key arguments. [6]