Worked solution from the Cost and management accounting (AS Level) MCQ booklet.
The question asks for the meaning of a stepped cost.
A stepped cost is fixed for a given level of output, then increases to a higher fixed amount when that level is passed.
So the answer is B.
A describes a semi-variable cost. C describes a fixed cost. D is wrong because a stepped cost does not vary with each unit.