Worked solution from the Cost and management accounting (AS Level) MCQ booklet.
The question asks how total supervisory salaries are classified when the business adds a supervisor to expand capacity.
Salaries stay fixed while output is within the capacity one supervisor can manage. When capacity grows, another supervisor is needed, and the total jumps up by a whole salary. A cost that is fixed within a range and then jumps is a stepped cost.
So the answer is C.
A is wrong because the total does not stay fixed once the range is exceeded. B is wrong because there is no variable part. D is wrong because the cost does not rise with every unit.