Worked solution from the Cost and management accounting (AS Level) MCQ booklet.
The question asks for the cost of manufacturing the order of 3 000 pairs.
Raw materials = $975
Packaging = 3 000 ÷ 50 = 60 packs × $4.20 = $252
Direct labour = $800
Direct labour hours = $800 ÷ $8.00 = 100 hours
Overheads absorbed = 100 hours × $6.25 = $625
Order setting up costs = $100
Total = $975 + $252 + $800 + $100 + $625 = $2 752
So the answer is D.
B ($2 652) leaves out the $100 setting up costs. A and C do not add the five items up correctly.
▶ Starts at Q25 (45:13)
Starts at Q25 (45:13) · by Study with Prashna. Tap the picture to open it on YouTube.
Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.