Worked solution from the The price system and the microeconomy MCQ booklet.
The question asks for the main aim of cost-benefit analysis (CBA).
CBA adds up all the costs and benefits of a project, private and external, and values them in money terms. A project is worthwhile when total benefit exceeds total cost.
When choosing between projects, the best one is the one with the highest positive difference between total benefit and total cost (the largest net benefit).
So the answer is D.
A is about a firm's private aim, not a social appraisal. B would give a net benefit of zero, which is not the aim. C is a tax policy, not what CBA does.
▶ Whole paper
Video solution of the whole paper · by Daniyal Aslam. Tap the picture to open it on YouTube.
Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.