Cambridge AS Level Accounting 9706 · 2.2 Traditional costing methods

Q253 · 9706/13/O/N/23 Q27

Worked solution from the Cost and management accounting (AS Level) MCQ booklet.

Q2539706/13/O/N/23original Q27Multiple choice
Question 27 from 9706/13/O/N/23

Worked solution

The question asks for the actual overheads in April.

Absorbed = actual direct labour hours × OAR = 6 100 × $20 = $122 000. (The rate is already given, so budgeted hours are not needed.)

Under-absorbed by $3 000 means actual overheads are $3 000 more than absorbed.

Actual overheads = $122 000 + $3 000 = $125 000.

So the answer is D.

A takes $3 000 off the budgeted amount ($120 000). B takes $3 000 off $122 000, which is the wrong direction. C adds $3 000 to $120 000 (the budgeted amount).

KEY IDEAActual overheads = absorbed overheads + under-absorption (or − over-absorption).
ANSWER D
VIDEO
▶ Starts at Q27 (39:33)

Starts at Q27 (39:33) · by Study with Prashna. Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.