Worked solution from the Cost and management accounting (AS Level) MCQ booklet.
The question asks by how much overheads are under or over absorbed.
Absorption rate = budgeted overheads ÷ budgeted machine hours = $560 000 ÷ 7 000 = $80 per hour.
Overhead absorbed = actual hours × rate = 6 700 × $80 = $536 000.
Actual overheads were $564 000. Absorbed $536 000 is less, so overheads were under absorbed by $28 000.
So the answer is D.
A and B only compare the two overhead totals ($4 000). C has the right amount but says over absorbed.