Cambridge A2 Level Business 9609 · 10.3 Investment appraisal

Q38 · 9609/33/O/N/25 Q3

Worked solution from the Finance and accounting Theory (Paper 3) booklet, Part 3 of 4.

Q389609/33/O/N/25original Q3Structured · 16 marks
Question 3 from 9609/33/O/N/25

Worked solution

(a)

Payback period is the time taken to recover the initial investment. Initial investment = $200m + $120m = $320m. Cumulative net cash flow: Year 2 $40m, Year 3 $120m, Year 4 $210m, Year 5 $310m, so $10m is still needed in Year 6. [1]

Months in Year 6 = $10m ÷ $120m × 12 = 1 month

Payback = 5 years 1 month (or 5.08 years) [1]

(b)

NPV = total discounted net cash flows − discounted capital cost

Total discounted inflows = 34.29 + 63.51 + 66.15 + 68.06 + 75.62 = $307.63m; discounted capital cost = 200.00 + 111.11 = $311.11m [1]

NPV = 307.63 − 311.11 = −$3.48m (accept −$3.5m) [1]

(c)

Verdict first: LBM's decision to go ahead is risky on the numbers but reasonable for the business's survival, so it should proceed only if it can protect itself against overspending.

Knowledge: investment appraisal such as payback and net present value (NPV) is quantitative and based on data, and NPV allows for the time value of money. But forecasts can be wrong as circumstances change, they can give a false sense of accuracy, and the people who supply the data may be biased. Qualitative factors also matter: attitude to risk, the effect on stakeholders (environmental and social) and how well the project fits the business objectives.

Application to the figures: payback is 5 years 1 month and the NPV over six years is −$3.48m. The mine is expected to last 15 years, but cash flows are only appraised for six years and are uncertain after that. LBM can afford the mine only if there are no adverse variances to the budget. It also faces local opposition and is already losing $2–3 million a year.

Analysis (against): the negative NPV over six years suggests the project does not cover its cost of capital, so going ahead could deepen LBM's existing losses. If adverse variances happen, LBM may run out of finance, the project could fail and the large initial investment ($200m + $120m) would be lost. Local opposition could also cause delays.

Analysis (for): the uncounted positive cash flows in Years 7–15, together with rapidly rising global demand for lithium (demand will be greater than supply after 2030), could make the NPV highly positive and raise future revenue. The price of lithium is likely to keep rising, and any other metals found in the water are not included in the data, so revenues may be higher than forecast. Heating local housing meets social aims and may reduce local opposition, which lowers the risk of delay. LBM would also learn from this first mine before the hard rock mine.

Evaluation: the NPV is very close to zero and the data covers only 6 of the 15 years, so the quantitative result is weak evidence and the qualitative factors may matter more. The decision depends on how reliable the cash flow estimates are for the last nine years, on how much financial and operational risk LBM will accept (tight budget, local opposition), and on how much the social benefit of heating housing is worth against the financial return. The risk appears fairly low because the finance is available, and if LBM does not go ahead it is likely to go out of business because its losses keep growing. LBM is the only lithium producer in country G and the government wants a long-term supply, so strategically the mine is needed.

Conclusion: LBM was right to go ahead because it must start mining to survive and gain from the forecast rise in revenue. However, it should check the cash flows for Years 7–15 (for example with a sensitivity analysis) and keep a finance buffer for adverse variances. If it cannot secure enough finance to absorb them, the project should be delayed or redesigned until a clearly positive NPV over the full 15 years can be shown.

This earns 2 marks for knowledge: developed knowledge of investment appraisal and qualitative factors. [2]

It earns 2 marks for application: developed application, using the case information (NPV, payback, 15-year life, tight finance, local opposition) at least twice. [2]

It earns 2 marks for analysis: developed analysis with two or more links in the chain, for example negative NPV → cost of capital not covered → deeper losses. [2]

It reaches the top level for evaluation: a developed, justified judgement in the business context that balances the key arguments and says what the decision depends on. [6]

KEY IDEAA project's NPV is only part of the decision: with a near-zero NPV and cash flows uncertain after six years, risk, finance and strategic need decide whether to go ahead.
TOTAL 16 marks

Official mark scheme

Mark scheme for 9609/33/O/N/25 question 3
VIDEO
▶ Topic lesson

A lesson on this topic · by Saifullah Ajaz . Tap the picture to open it on YouTube.

Solutions follow the official Cambridge mark schemes; marks are shown in grey. Videos are from other YouTube channels. Paper codes read component / series / year: M/J = May/June, O/N = October/November. Past-paper questions © UCLES, reproduced for classroom practice.