9609/42/O/N/25 question 1: worked solution (October/November 2025, paper 42)

Show as plain text

Cambridge A2 Level Business 9609 · 9.3 Operations strategy Worked solution from the Operations management Theory (Paper 4) booklet, Part 3 of 3. Q49 9609/42/O/N/25 original Q1 Structured · 20 marks Worked solution (a) Evaluate means: weigh up how well the strategy worked, using points for and against, then give a judgement. Use the case's own facts and dates. Knowledge: KK's operations strategy is built on lean production , which aims to cut waste and response times. Its tools include critical path analysis (CPA) , simultaneous engineering , just in time (JIT) and kaizen , the idea of continuous improvement involving all employees. Application: KK is a labour intensive social enterprise in the primary sector, farming kelp, and its mission is the most efficient use of natural resources. In 2020 it used a network diagram (Appendix 1) with three teams working in parallel to build its $5 million refinery. In 2021 it introduced JIT (Appendix 2). In 2022 the Managing Director described an employee suggestion box to collect improvement ideas (kaizen) and a zero waste refinery. Analysis (JIT worked): Before JIT kelp was harvested weekly, dried for five days, bagged and stored. After JIT it is harvested daily and sent straight to manufacturers, unprocessed. This removes drying, packing and storage, so inventory and processing costs fall , which raises profit and supports the zero waste aim. Analysis (CPA and simultaneous engineering worked): The network shows a critical path of 36 months (1-3-5-6-7). Running the purchasing, construction and human resource teams at the same time shortens the project, and exterior construction finished a month early (15 months, not 16), so the refinery could open sooner and start earning. Analysis (kaizen worked): An employee suggestion box lets all workers suggest small changes, which can lower costs and raise productivity. However, in 2021 workers' representatives met management about poor motivation , so staff may not take part fully, and this weakens the effect. Analysis (against): The planning was not fully effective. Recruitment and training (activity 4-6) began six months late because of the skills shortage in country W , which puts the project behind. Sales rose 200% in 2022 but the lead time for customer orders rose from one week to one month , because JIT leaves no stock to meet a sudden rise in demand, so customers may be lost. Analysis (against): The new refinery operated at only 40% capacity in 2023 and only 50% of kelp was processed in it. Capacity is badly under-used, so the high fixed costs of a $5 million refinery (mostly borrowed) are spread over few units and unit costs stay high. In 2024 KK began importing kelp from lower-income countries to keep the refinery supplied, which suggests its own kelp supply was not enough. Evaluation: JIT was the most effective element, because it cut costs and waste straight away, whereas the refinery project was the least effective , being late in training and under-used. Overall, KK's strategy was partly effective : good at cutting waste and building quickly, weak at matching capacity and demand. Its effectiveness depends on whether KK can keep reliable supplies of kelp, solve the skills shortage and keep staff motivated. KK could also have used flexible, capacity-matching planning to avoid long lead times. My judgement is that the strategy was only moderately effective between 2020 and 2024, since 40% capacity and a month's lead time show the planning did not fit demand, even though the cost savings were real and the sustainability aims were kept. This earns the top level for knowledge (up to 3): lean production, JIT, kaizen, CPA and simultaneous engineering are named and explained. [3] This earns the top level for application (2): developed use of KK's own facts, such as the 2021 JIT change, the six-month training delay, 40% capacity and the lead time rising from one week to one month. [2] This reaches the top level for analysis (8): each element is analysed in context with a chain of cause and effect and then balanced by a counter-point, done more than once. [8] This reaches the top level for evaluation (7): a justified judgement on the most and least effective elements and overall effectiveness, in context, with what it depends on. [7] KEY IDEA A lean strategy cuts waste and cost, but it must also match capacity and customer demand, or lead times grow and capacity goes unused. TOTAL 20 marks Official mark scheme VIDEO ▶ Topic lesson A lesson on this topic · by Saifullah Ajaz . Tap the picture to open it on YouTube.