Worked solution from the Cost and management accounting (AS Level) MCQ booklet.
The question asks what causes over-absorption when the rate is per direct labour hour.
Overheads absorbed = actual labour hours × rate. Over-absorption happens when absorbed overheads are more than the overheads incurred.
1 is a cause: more hours than budgeted means more overhead is absorbed.
2 is a cause: more products made than budgeted means more hours, so more is absorbed.
3 is not a cause: absorption depends on production, not on units sold.
So 1 and 2 only.
So the answer is B.
A, C and D include 3.